Skip Ribbon Commands
Skip to main content

Construction Updates

On-site construction began in May 2020 and will take approximately 24 months to complete. At that time, some work will remain, including the removal of the existing Hawkins Point and Sollers Point terminal stations.

Throughout the construction of the Key Crossing Reliability Initiative project, BGE will regularly provide updates on project progress:

On-site construction activities week of 4/13/2022

  • Performing cathodic protection and grounding at Tower 3 and Tower 4
  • Preparing concrete and installing fender system at Tower 2, Tower 3, and Tower 4 structures
  • Installing metal materials at Tower 3 structure
  • Installing avian mitigation tools at Tower 3, Tower 4, and Tower 5
  • Installing davit cranes at Tower 2, Tower 3, and Tower 4
  • Installing waring signs at Tower 2, Tower 3, Tower 4, Tower 5, and Tower 6
  • Mobilizing barges in water and relocating as needed to get work completed

On-site construction activities week of 4/6/2022

  • Performing cathodic protection and grounding at Tower 3 and Tower 4
  • Preparing concrete and installing fender system at Tower 3 and Tower 4 vessel collision protection structures
  • Performing pile coating repairs at Tower 2 structures
  • Installing metal materials at Tower 4 and Tower 5 structures
  • Installing davit crane at Tower 6
  • Installing solar panels and batteries at Tower 2, Tower 3, Tower 4, Tower 5, Tower 6, and Tower 7
  • Mobilizing barges in water and relocating as needed to get work completed

On-site construction activities week of 3/30/2022

  • Performing cathodic protection and grounding at Tower 2, Tower 3, Tower 4, Tower 5, and Tower 6
  • Installing fender system and anodes at Tower 3 and Tower 4 structures
  • Installing fencing at Tower 4 foundation and vessel collision protection structure
  • Installing metal materials at Tower 3, Tower 4, and Tower 5 structures
  • Installing davit cranes at Tower 2, Tower 3, Tower 4, Tower 5, and Tower 6
  • Installing FAA lighting at Tower 1, Tower 6, and Tower 7
  • Mobilizing barges in water and relocating as needed to get work completed
© Baltimore Gas and Electric Company, 2023. All Rights Reserved.