Skip Ribbon Commands
Skip to main content

Construction Updates

On-site construction began in May 2020 and will take approximately 24 months to complete. At that time, some work will remain, including the removal of the existing Hawkins Point and Sollers Point terminal stations.

Throughout the construction of the Key Crossing Reliability Initiative project, BGE will regularly provide updates on project progress:

On-site construction activities week of 9/30/2020

  • Removing temporary pile guides at Tower 4
  • Installing rebar cages at Tower 6 foundation pile
  • Installing temporary pile guides and production piles at Tower 5
  • Installing formwork on the pre-cast foundation slabs for Tower 5
  • Performing splicing on Tower 7 production pile and Tower 3 foundation pile
  • Driving production pile at Tower 7
  • Mobilizing barges in water and relocating as needed to get work completed
  • Monitoring vibration activity from impact hammer used during pile driving
On-site construction activities week of 9/23/2020
  • Installing temporary pile guides at Tower 2 and Tower 5
  • Installing production piles at Tower 5
  • Installing production piles at Tower 2
  • Installing formwork on the pre-cast foundation slabs for Tower 5 and Tower 6
  • Performing splicing on Tower 7 production piles
  • Driving production pile at Tower 7
  • Installing Anchor Bolt Cage support pad at Tower 7 foundation
  • Mobilizing barges in water and relocating as needed to get work completed
  • Monitoring vibration activity from impact hammer used during pile driving
On-site construction activities week of 9/16/2020
  • Re-striking test pile at Tower 3
  • Re-striking test piles at Tower 4
  • Installing temporary piles guides at Tower 2
  • Performing splicing on Tower 7 production piles
  • Driving production pile at Tower 7
  • Loading Tower 5 production piles on to barge
  • Mobilizing barges in water and relocating as needed to get work completed
  • Monitoring vibration activity from impact hammer used during pile driving

© Baltimore Gas and Electric Company, 2020. All Rights Reserved.